SR-50 Utility Relocation Project (FDOT JPA)
- End Market: W/WW Distribution, Transmission, Collection
- Services Provided:
- Construction Administration
- Ecological Services
- Landscape Architecture, Urban Design & Planning
- MEP
- Permit Management
- Surveying & Mapping
- Utility Engineering
- Project Size: Approximately 1.1 miles of existing OCU water and wastewater mains had to be relocated. The relocation within FDOT right-of-way consisted of approximately 2,200 LF of 12-inch and 5,150 LF of 20-inch water main, and 5,000 LF of 24-inch force main. The project also had 600 LF of 30-inch directional drill, 200 LF aerial crossing, and multiple water and wastewater service reconnections.